Phase 3 of Hoggs Hollow Stormwater and Road Improvement Project Begins!

As I mentioned in April, the first and second phase of the city’s $24-million Hoggs Hollow stormwater management and road improvements project are complete and construction on the third phase has just begun.

Construction is starting soon on the following streets:

  • Donwoods Drive from Knightswood Road to Donino Avenue;
  • Donwoods Grove;
  • Winton Road;
  • Plymbridge Road from the bridge to Donwoods Drive; and,
  • Donwoods Drive from Donino Avenue to Ivor Road.

The work involves storm sewer installation and road reconstruction. Phase IV is set to get underway in the second half of 2014.

See the construction notice below for more information.

For more information about any aspect of the project, you can contact Manveer Ramburrun, the Project Engineer, at mrambur@toronto.ca or (416) 395-1112.

York Ridge and Don Ridge stormwater management and road improvements

This summer the city will be reconstructing streets, installing storm sewers and gutter on York Ridge Road and Don Ridge Drive as part of a road and stormwater management improvement project on the following streets:

  • York Ridge Road from York Mills Road to Old Yonge Street
  • Don Ridge Drive from the west end to Old Yonge Street

As part of this project, the city will also be replacing its portion of any substandard water service to ensure the safe and efficient delivery of water and improve drinking water quality.

For more information about any aspect of the project, you can contact Manveer Ramburrun, the Project Engineer, at mrambur@toronto.ca or (416) 395-1112.

Hoggs Hollow Stormwater Management Update

Phases I and II of the city’s $24 million Hoggs Hollow road and stormwater management project are complete, and Phases III and IV are on schedule for completion in 2014.

The city recently awarded the contract for Phase III to Clearway, and construction will begin in early spring on the following streets:

  • Donwoods Drive from Knightswood Road to Donino Avenue;
  • Donwoods Grove;
  • Winton Road;
  • Plymbridge Road from the bridge to Donwoods Drive; and,
  • Donwoods Drive from Donino Avenue to Ivor Road.

The work involves storm sewer installation and road reconstruction. The water main on Winton Road will also be replaced. Phase IV is set to get underway in the second half of 2014.

For more information about any aspect of the project, you can contact Manveer Ramburrun, the Project Engineer, at mrambur@toronto.ca or (416) 395-1112.